1. A department asks you to "project-manage" the monthly invoice run, which has no end date and the same steps every cycle. What is it?
2. What does a signed project charter primarily give you as project manager?
3. The sponsor wants the original go-live date and a late feature add, with no extra budget. What should you do first?
4. A stakeholder messages you: "While you are building the report, can you add an extra dashboard? It should only take a day." You have no spare contingency. What is the correct next step?
5. What should a WBS primarily break down?
6. Which statement is a usable acceptance criterion?
7. What does the critical path represent?
8. Task B cannot start until Task A is finished. What dependency is that?
9. A developer wants to add two extra days to every estimate "for safety." What is the better practice?
10. The test environment is already down and UAT cannot run. Where does this belong?
11. You add a second supplier and extra design review now so a late drop is less likely and less damaging. What is that?
12. When should you activate a contingency plan?
13. A director can stop your release but rarely reads long updates and is not involved day to day. How should you engage them?
14. What belongs near the top of a weekly status to a sponsor?
15. Two managers both insist they are "accountable" for go-live sign-off. What should you do?